| 1 |
Kushi Nagar |
8039028 |
BADARAHA GRAM PANCHAYAT WS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
105.16 |
79.94 |
79.94 |
0.00 |
25.22 |
105.16 |
Under Construction |
38.00 |
1.Electrification work pending.
2. OHT not started, (Waterlogged in Current time.) Contractor is agree for start work once the waterlogging has been cleared.
3. Rising main (30m) pending
4. Boundrywallpending, 5. Approx 2 km Distribution system and 250 FHTC pending. |
| 2 |
Kushi Nagar |
8127407 |
MAILA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
156.41 |
102.16 |
102.16 |
0.00 |
54.25 |
156.41 |
Under Construction |
5.00 |
Land not aviliable in this village which is informed by Revenue Department in written. And we are trying/Approach for land in other nearby village. |