| 1 |
Kushi Nagar |
7892835 |
Ahladpur EMWQ Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
287.37 |
106.88 |
106.88 |
0.00 |
180.49 |
287.37 |
Under Construction |
66.00 |
1.Electric Connection and Pumping Plant pending
2. OHT column pipe, Staircase, Railing, SV and SV chamber, OHT finishing pending, 3.Pumphouse at Sill level and boundrywall pending, 4. Staff quarter finishing pending , 5. approx 7 km Distribution system and approx 580 FHTC pending. |
| 2 |
Kushi Nagar |
7894059 |
Lachhia Deoria GOV AES JE Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
439.29 |
206.33 |
206.33 |
0.00 |
232.96 |
439.29 |
Under Construction |
67.00 |
1. OHT top dome, column pipe, Staircase, Railing, SV and SV chamber, finishing pending, 2. Rising main (330m) pending , 3. approx 7.5 km Distribution system and approx 775FHTC pending. |
| 3 |
Kushi Nagar |
7894075 |
Gagalwa EMWQ |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
332.01 |
256.32 |
256.32 |
0.00 |
75.69 |
332.01 |
Under Construction |
67.00 |
1. Pumping plant and Electrification is pending.
2. Rising main(30m) pending,
3.Pumphouse, boundrywall and staff quarter finishing work pending,
4. Approx 7.7 km distribution system and approx 300 FHTC pending. |
| 4 |
Kushi Nagar |
7924199 |
PARSAUNI GP WSS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
214.31 |
168.14 |
168.14 |
0.00 |
46.17 |
214.31 |
Under Construction |
68.00 |
1. Pumping plant and Electrification is pending, 2. Rising main (30m)pending,
3. OHT column pipe, Staircase, Railing, SV and SV chamber, Apron, finishing pending,
4.boundry wall and Staff quarter finishing pending ,
5. approx 4.7 km Distribution system and approx 475 FHTC pending. |
| 5 |
Kushi Nagar |
8132396 |
HATHIYA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
133.55 |
126.96 |
126.96 |
0.00 |
6.59 |
133.55 |
Under Construction |
60.00 |
1. OHT work pending, only excavation done,
2. Boundrywall, pumphouse and staff quarter finishing pending
3. Approx 100 FHTC pending, Direct pumping is going on. |