S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Ghazipur 7854869 Bara WORLD BANK Jal Nigam YES NO NO 1616.39 1616.39 1616.39 0.00 0.00 1616.39 Under Construction 85.00 1. Project cost exceeded SLSSC cost. 2. DPR Prepared and will be submitted by 15th Oct 26 3. After approval of the same, work will be completed.
2 Ghazipur 7855169 Tiwaripur GOV WORLD BANK Jal Nigam YES NO NO 531.30 279.27 279.27 0.00 252.03 531.30 Under Construction 80.00 1. notice for cancellation of tender served on date 01.07.2026 and last Notice served by CE sir on 18.09.2026. 2. After cancellation new short term tender can be invited.
3 Ghazipur 7866260 Sadhopur urf Rampur WORLD BANK Jal Nigam YES NO NO 253.44 29.88 29.88 0.00 223.56 253.44 Under Construction 70.00 1. Re tendering done and work allotted with start date 16.09.2026. 2. Pipe line work completed. 3. RCC Tank work (bottom dome, vertical wall and top dome) in progress and will be completed by 30/12/2026