| S.No. | District | Scheme ID | Scheme Name | Program Name | Department | PWS Exist | Physical Completion | Financial Completion | Work Cost | Released Cost | Expenditure Cost | Liability | Balance Fund | Final Cost | Scheme Status | Physical Progress(%) | Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | 7866260 | Sadhopur urf Rampur | WORLD BANK | Jal Nigam | YES | NO | NO | 253.44 | 29.88 | 29.88 | 0.00 | 223.56 | 253.44 | Under Construction | 70.00 | 1. Re tendering done and work allotted with start date 16.09.2026. 2. Pipe line work completed. 3. RCC Tank work (bottom dome, vertical wall and top dome) in progress and will be completed by 30/12/2026 |