| S.No. | District | Agency | Scheme Id | Scheme Name | Phase | No.Of.Village | T/W Approved | T/W Completed | Total OHT | OHT Completed | Distribution Line Laying Approved(KM) | Distribution Line Laying Completed(KM) | Har Gar Jal Villages | HGJ Certified Villages | Handed Over Villages |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total | 4 | 2 | 2 | 2 | 2 | 12.56 | 11.98 | 2 | 1 | 0 | |||||
| 1 | Saharanpur | GA INFRA - BABA (JV) | 20067471 | MAHMOODPUR | PHASE-3 | 3 | 1 | 1 | 1 | 1 | 7.48 | 7.48 | 1 | 0 | 0 |
| 2 | Saharanpur | GA INFRA - BABA (JV) | 20072177 | DAIDNOR | PHASE-3 | 1 | 1 | 1 | 1 | 1 | 5.08 | 4.50 | 1 | 1 | 0 |