Project Completion Certificate Details

Sr. No. District Name Agency Name Scheme Code Scheme Name Covered Villages Covered Habitations Covered Population Base Year Intermediate Year Design Year Contract Completion Date Actual Completion Date Trial Run Date O&M Start Date TPI Fill Status TPI Remark EE Status EE Remark View
1 Balrampur Larsen & Toubro Ltd 20016384 Ararpakar water supply scheme 2 10 4974 2022 2037 2052 30-Dec-2021 05-May-2025 05-Aug-2025 05-Aug-2025 Vide letter no.: ceinsys/OPR/Devipatan/BLP/O&M/UPJN/2o26-27/07/210 mentioning that scheme is partially commissioned and not yet ready for O&M handover. Major deficiencies remain in FHTC coverage, commissioning of four habitations, tail-end water pressure, leakage, chlorination, SCADA/instrument calibration, automation, and essential civil/E&M works. All pending works, testing, calibration, water-quality assurance, and rectification should be completed before O&M handover. Some FHTCs and other minor campus related works to be rectified. View
2 Balrampur Larsen & Toubro Ltd 20018772 Dandav water supply scheme 1 3 3784 2022 2037 2052 30-Jun-2023 05-May-2025 05-Aug-2025 05-Aug-2025 Vide letter no. ceinsys/OPR/Devipatan/BLP/O&M/UPJN/2026-27 /07/309 dated 28.07.2026 mentioning that the scheme is partially commissioned and presently offer for O&M handover. Although FHTCs and automation systems are largely installed and water supply with chlorination is operational in two habitations, significant deficiencies remain in leakage rectification, pressure management, OHT hydrotesting, civil/campus works, calibration, SCADA integration, safety provisions, and the pending OHT honeycomb NC. All open NCs and deficiencies should be rectified, tested, and duly verified before final commissioning and O&M handover. Some FHTCs and other minor campus related works to be rectified. View
3 Balrampur Larsen & Toubro Ltd 20092907 Ganveria Bujurg Water Supply Scheme 1 3 2512 2022 2039 2052 28-Oct-2024 06-Sep-2025 06-Dec-2025 06-Dec-2025 • Distribution: -Total scope of laying is 7986 km, total pipe laid is 8312 km, which is beyond the scope. • FHTC: -Total scope is 283 no’s, in which 243 Executed on sit as per list attached. • Automation & Chlorination: -Automation System was found functional, but Calibration was not done & Chlorine was in function. All Installed Automation Equipment were Successfully displayed on the SCADA/HMI Platforms. • Water is being supplied through OHT and chlorination unit functional during site inspection. • Water is being supplied only for 2 Habitation out of 3 habitations, with chlorination treatment. • Water is being Supplied by OHT, Hydrotest of OHT has not been Performed. Campus development: - Campus development is not done but Housekeeping is required. Some FHTCs and other minor campus related works to be rectified. View
4 Balrampur Larsen & Toubro Ltd 20018767 Gobari water supply scheme 2 4 3697 2022 2037 2052 30-Dec-2021 31-Aug-2024 31-Aug-2024 31-Aug-2024 vide letter no. Lette r No.- Cei nsys/o PR/Devi pata n/B LP /o&m /UP JN /2026-27/ 07/102 dated 8.07.2026 mentioning The most critical concern is that water supply is not reaching three out of four habitations, while major leakages and low pressure are affecting the distribution network. In addition, the automation and SCADA systems are not functional, the chlorine dosing system is not demonstrating the approved dosing level, and essential testing, calibration, earthing, lightning protection, and documentation remain incomplete. Some FHTCs and other minor campus related works to be rectified. View
5 Balrampur Larsen & Toubro Ltd 20019344 Jamuni Kalan water supply scheme 1 3 2262 2022 2037 2052 26-Jun-2023 06-Feb-2024 06-May-2024 07-May-2024 Approved as per theTKC agreement. ok View
6 Balrampur Larsen & Toubro Ltd 20069285 Khagaijot Water Supply 1 6 4814 2022 2037 2052 27-Feb-2023 16-Dec-2025 16-Mar-2026 16-Mar-2026 After completion of all rectification works, the scheme should undergo a joint re-inspection and functional performance test by the Executing Agency/TKC, TPI, and UPJN Engineer. The O&M handover should be considered only after satisfactory closure of all observations, successful commissioning, verification of water supply in all intended habitations, confirmation of proper chlorination and pressure, and submission of all requisite technical documents and test certificates. Some FHTCs and other minor campus related works to be rectified. View
7 Balrampur Larsen & Toubro Ltd 20016392 Luchuiya water supply scheme 1 5 3269 2022 2037 2052 30-Dec-2024 30-May-2024 30-Aug-2024 01-Sep-2024 ok Ok View
8 Balrampur Larsen & Toubro Ltd 20024855 Peher Water Supply Scheme 2 3 4300 2022 2037 2052 31-Dec-2026 06-Sep-2025 06-Dec-2025 07-Dec-2025 Based on the site inspection and the observations recorded under the Distribution Pipeline & FHTC, Pump House, OHT, Boundary Wall & Campus Development, and E&M works, it is observed that several important construction, finishing, testing, documentation, and functional works are still incomplete or require rectification. After completion of the above rectification works, the scheme should be jointly re-inspected and functionally tested by the concerned TKC/Executing Agency, TPI, and UPJN Engineer. Transfer to the O&M Phase may be considered only after satisfactory verification of the completed works, successful functional testing, submission of all required documents, and confirmation that the scheme is capable of providing continuous and safe water supply to all intended habitations. Some FHTCs and other minor campus related works to be rectified. View
9 Balrampur Larsen & Toubro Ltd 20102005 PUREY CHEETAN WATER SUPPLY SCHEME 1 1 1123 2022 2037 2052 24-Sep-2024 06-Sep-2025 06-Dec-2025 06-Dec-2025 incomplete earthing and lightning protection, pending E&I testing/calibration, and non-submission of required drawings, certificates, and test reports. Some FHTCs and other minor campus related works to be rectified. View
10 Balrampur Larsen & Toubro Ltd 20094192 Razderwa Tharoo Water Supply Scheme 2 2 2200 2022 2037 2052 25-Mar-2025 06-Dec-2025 06-Dec-2025 06-Dec-2025 Vide letter no. ceinsys/0PR/Devipatan/BLP/O&M/UPJN/202607/07/308 dated 28.07.2026 Distribution :-Total scope of laying is 6427 km, total pipe laid is 7314 km, which is beyond the scope. FHTC: -Total scope is 276 no's, in which 276 Executed on Sit as per list attached. Automation & Chlorination: -Automation System was found non-functional. Water is being Supplied through OHT and chlorination unit non-functional during site inspection. Water is being supplied for 1 habitation out Of 2 habitations. Water is being Supplied by OHT, Hydrotest of OHT has not been Performed. Campus-development: Campus development is not done but Housekeeping is required. Some FHTCs and other minor campus related works to be rectified. View
11 Balrampur Larsen & Toubro Ltd 20021254 Sarai Khas Water Supply Scheme 1 6 4814 2022 2037 2052 27-Feb-2023 16-Dec-2025 16-Mar-2026 16-Mar-2026 The work mentioned above is pending and needs to be addressed as a priority. The scheme can only be considered for commissioning and subsequent Operation & Maintenance (O&M) phase after all issues are resolved and compliance with DPR specifications is ensured. ok View
12 Balrampur Larsen & Toubro Ltd 20098092 SOWNAHWA & HARIHARPUR WATER SUPPLY SCHEME 1 1 2050 2022 2037 2052 31-Dec-2026 06-Sep-2025 06-Dec-2025 06-Dec-2025 ok OK View
13 Balrampur Larsen & Toubro Ltd 20094052 TENDUA NAGAR WATER SUPPLY SCHEME 2 4 2000 2022 2037 2052 28-Apr-2023 06-Sep-2025 06-Dec-2025 06-Dec-2025 Vide letter no.Ceinsys/O PR/Devipatan/BlP / O &Ml/ UPJN / 2 02 6 -27 / 07 / 2 09 dated 21.07.2026 mentioning that the scheme is partially commissioned and operational, with FHTCs provided in some habitations; however, several critical deficiencies remain in distribution, civil works, O&M, and E&M/SCADA systems. Key issues include incomplete connectivity to the second revenue village due to pending forest permission, low tail-end pressure, incomplete FHTC works, non-functional/incomplete SCADA and chlorination interlocks, absence of required flow-metering and earthing provisions, and various defects in the pump house. Some FHTCs and other minor campus related works to be rectified. View
14 Balrampur Larsen & Toubro Ltd 20016395 Udaipur water supply scheme 2 5 1627 2022 2037 2052 30-Dec-2024 06-Feb-2024 06-May-2024 07-May-2024 OK Ok...... View