Vide letter no.: ceinsys/OPR/Devipatan/BLP/O&M/UPJN/2o26-27/07/210 mentioning that scheme is partially commissioned and not yet ready for O&M handover. Major deficiencies remain in FHTC coverage, commissioning of four habitations, tail-end water pressure, leakage, chlorination, SCADA/instrument calibration, automation, and essential civil/E&M works. All pending works, testing, calibration, water-quality assurance, and rectification should be completed before O&M handover.
Some FHTCs and other minor campus related works to be rectified.
Vide letter no. ceinsys/OPR/Devipatan/BLP/O&M/UPJN/2026-27 /07/309 dated 28.07.2026 mentioning that the scheme is partially commissioned and presently offer for O&M handover. Although FHTCs and automation systems are largely installed and water supply with chlorination is operational in two habitations, significant deficiencies remain in leakage rectification, pressure management, OHT hydrotesting, civil/campus works, calibration, SCADA integration, safety provisions, and the pending OHT honeycomb NC. All open NCs and deficiencies should be rectified, tested, and duly verified before final commissioning and O&M handover.
Some FHTCs and other minor campus related works to be rectified.
• Distribution: -Total scope of laying is 7986 km, total pipe laid is 8312 km, which is beyond the scope.
• FHTC: -Total scope is 283 no’s, in which 243 Executed on sit as per list attached.
• Automation & Chlorination: -Automation System was found functional, but Calibration was not done & Chlorine was in function. All Installed Automation Equipment were Successfully displayed on the SCADA/HMI Platforms.
• Water is being supplied through OHT and chlorination unit functional during site inspection.
• Water is being supplied only for 2 Habitation out of 3 habitations, with chlorination treatment.
• Water is being Supplied by OHT, Hydrotest of OHT has not been Performed.
Campus development: - Campus development is not done but Housekeeping is required.
Some FHTCs and other minor campus related works to be rectified.
vide letter no. Lette r No.- Cei nsys/o PR/Devi pata n/B LP /o&m /UP JN /2026-27/ 07/102 dated 8.07.2026 mentioning The most critical concern is that water supply is not reaching three out of four habitations, while major leakages and low pressure are affecting the distribution network. In addition, the automation and SCADA systems are not functional, the chlorine dosing system is not demonstrating the approved dosing level, and essential testing, calibration, earthing, lightning protection, and documentation remain incomplete.
Some FHTCs and other minor campus related works to be rectified.
After completion of all rectification works, the scheme should undergo a joint re-inspection and functional performance test by the Executing Agency/TKC, TPI, and UPJN Engineer. The O&M handover should be considered only after satisfactory closure of all observations, successful commissioning, verification of water supply in all intended habitations, confirmation of proper chlorination and pressure, and submission of all requisite technical documents and test certificates.
Some FHTCs and other minor campus related works to be rectified.
Based on the site inspection and the observations recorded under the Distribution Pipeline & FHTC, Pump House, OHT, Boundary Wall & Campus Development, and E&M works, it is observed that several important construction, finishing, testing, documentation, and functional works are still incomplete or require rectification.
After completion of the above rectification works, the scheme should be jointly re-inspected and functionally tested by the concerned TKC/Executing Agency, TPI, and UPJN Engineer. Transfer to the O&M Phase may be considered only after satisfactory verification of the completed works, successful functional testing, submission of all required documents, and confirmation that the scheme is capable of providing continuous and safe water supply to all intended habitations.
Some FHTCs and other minor campus related works to be rectified.
incomplete earthing and lightning protection, pending E&I testing/calibration, and non-submission of required drawings, certificates, and test reports.
Some FHTCs and other minor campus related works to be rectified.
Vide letter no. ceinsys/0PR/Devipatan/BLP/O&M/UPJN/202607/07/308 dated 28.07.2026
Distribution :-Total scope of laying is 6427 km, total pipe laid is 7314 km, which is beyond the
scope.
FHTC: -Total scope is 276 no's, in which 276 Executed on Sit as per list attached.
Automation & Chlorination: -Automation System was found non-functional.
Water is being Supplied through OHT and chlorination unit non-functional during site inspection.
Water is being supplied for 1 habitation out Of 2 habitations.
Water is being Supplied by OHT, Hydrotest of OHT has not been Performed.
Campus-development: Campus development is not done but Housekeeping is required.
Some FHTCs and other minor campus related works to be rectified.
The work mentioned above is pending and needs to be addressed as a priority. The scheme can only be considered
for commissioning and subsequent Operation & Maintenance (O&M) phase after all issues are resolved and
compliance with DPR specifications is ensured.
Vide letter no.Ceinsys/O PR/Devipatan/BlP / O &Ml/ UPJN / 2 02 6 -27 / 07 / 2 09 dated 21.07.2026 mentioning that the scheme is partially commissioned and operational, with FHTCs provided in some habitations; however, several critical deficiencies remain in distribution, civil works, O&M, and E&M/SCADA systems. Key issues include incomplete connectivity to the second revenue village due to pending forest permission, low tail-end pressure, incomplete FHTC works, non-functional/incomplete SCADA and chlorination interlocks, absence of required flow-metering and earthing provisions, and various defects in the pump house.
Some FHTCs and other minor campus related works to be rectified.